Question # 1

At the end of an 8-hour electrical shutdown, after the maintenance work is completed but before the cabinets are closed up or the system re-energized, a final inspection should be completed by individuals who have

A.

been involved since the beginning of the shutdown.

B.

"fresh eyes" and go/no go authority.

C.

working knowledge of the generators and switch gear.

D.

gathered feedback and attended the lessons learned debriefing.

Question # 2

In accordance with The Joint Commission's Emergency Management Chapter, which of the following is one of the most effective tools to plan an emergency response exercise?

A.

ILSM

B.

PCRA

C.

HVA

D.

ICRMR

Question # 3

Which of the following Environment of Care (EOC) management plans requires inspecting buildings/facilities and grounds to identify hazardous conditions?

A.

Utilities Management

B.

Hazardous Materials Management

C.

Safety and Security Management

D.

Fire Safety Management

Question # 4

If a boiler combustion efficiency test indicates 22% excess oxygen at mid-firing rate, which of the following adjustments should be made?

A.

Shift to steam atomization.

B.

Increase the nozzle air pressure.

C.

No adjustment is necessary.

D.

Increase the fuel pressure.

Question # 5

A "WAGD" outlet would typically be found in the

A.

boiler room.

B.

electrical closet.

C.

laundry room.

D.

operating room.

Question # 6

To minimize the number of change orders, it is best to have

A.

complete plans and specifications.

B.

a builder's insurance policy and performance bond.

C.

multiple prequalified bidders.

D.

a qualified construction manager and subcontractors.

Question # 7

Costs to overhaul an AHU to the extent that the life of the equipment is extended for five years are considered what type of cost?

A.

operating

B.

capital

C.

non-depreciable

D.

contingency

Question # 8

Which of the following techniques are used for predictive maintenance?

vibration monitoring

oil analysis

PM frequency analysis

ultrasound

A.

1, 2, and 3 only

B.

1, 2, and 4 only

C.

1, 3, and 4 only

D.

2, 3, and 4 only

Question # 9

During an analysis of a recent fire alarm log, a higher-than-normal incidence of construction-related fire alarm activations is discovered. The following tasks must be performed:

The hospital evaluates actions to confirm that they resulted in improvements.

The hospital takes action when it does not achieve or sustain planned improvements.

The facility manager identifies and prioritizes improvement opportunities.

The hospital takes action on improvement priorities.

What is the most effective procedural sequence?

A.

4, 3, 1, 2

B.

3, 4, 2, 1

C.

3, 4, 1, 2

D.

4, 3, 2, 1

Question # 10

In the design of a new bone marrow unit within an existing hospital, there are 10 protective environment rooms. The area of each room is 140 sq. ft. with an 8-ft. ceiling height. All rooms are served by a single AHU. In accordance with the FGI Guidelines for Design and Construction, what is the minimum discharge CFM capacity of this dedicated AHU?

A.

1,867

B.

2,240

C.

2,800

D.

3,733