You need a new project to track Software Defects.
The entire setup should be identical to the Hardware Defect project.
You ask your Jira administrator to create a new project with a shared configuration, and use the Hardware Defect project as the source.
Which three elements will you need to manually configure to achieve an identical setup? (Choose three.)
As a project administrator, what changes can you make to the project sidebar?
You manage multiple projects which share a notification scheme.
For the Issue Moved event, you want to notify only a particular individual.
That individual needs to be selected by other users.
Which value should be used for the Issue Moved event?
Your Scrum Software type project only uses a single shared workflow.
The resolution needs to be set manually during the Fix transition.
As a project administrator, how can you achieve this?
You want a built-in report that meets these requirements:
shows the results of a saved filter
groups the results by priority and shows a progress bar for each priority
displays issue status and resolution
Which report should you use?
You want a dashboard to display the following information:
the number of issues in progress
the number of issues per assignee
the number of issues per issue type
the number of issues created in the last 30 days
Additionally, it should only display data from a specific project.
Which system gadget will definitely NOT meet the requirements?
For the DEV project, Max has these requirements relating to time logging:
I need to be able to edit time logs.
I need to be able to delete time logs.
Which three project permissions does Max need in order to meet these requirements? (Choose three.)
Tom needs to work on scheduling and reordering future Sprints in a project.
What are the minimum two permissions that Tom needs? (Choose two.)
All projects use only a single simplified workflow which has three statuses (Open, In Progress, Closed) and all global transitions.
You need to find all issues that were in the Closed status at some point in their lifecycle.
Select the correct JQL query.
Elaine is the project administrator for the Finance project.
The team requests a brand new field called Currency. It must be added to the screen used on the Approval transition. How can these requirements be met?