Pre-Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 3
Total 28 questions
Exam Code: AD0-E911                Update: May 26, 2026
Exam Name: Adobe Workfront Project Manager Certified Professional

Adobe Adobe Workfront Project Manager Certified Professional AD0-E911 Exam Dumps: Updated Questions & Answers (May 2026)

Question # 1

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.

B.

Add a new billing rate to all tasks that involve video editing.

C.

Add a new billing rate within the project.

Question # 2

What is unique to a Scrum iteration?

A.

Backlog of stories and issues

B.

Workload Balancer for assigning users to tasks

C.

Burndown Chart

Question # 3

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

A.

Status

B.

Condition

C.

Progress Status

Question # 4

An organization has created unique data fields relevant to their projects. Starting by navigating from a project ' s landing page, where is this data found?

A.

Project Details > Custom Forms

B.

Project Details > Overview

C.

Business Case > Project Info

Question # 5

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

A.

Late

B.

At Risk

C.

In Trouble

Question # 6

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

A.

Actual Completion Date

B.

Progress Status

C.

Status

Question # 7

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Question # 8

A project manager compares the original schedule for a task to another set of dates that moved later after predecessors slipped and the assignee changed a completion commitment.

What do these later, system-calculated dates represent?

A.

They are Planned Dates that show the originally scheduled task dates.

B.

They are Projected Dates that show the current forecast for task start and finish.

C.

They are Milestone Path Dates that show when milestone tasks are expected to occur.

Question # 9

In the approval path shown below, which Project Status will the Project be if rejected?

A.

Rejected

B.

Current

C.

Requested

Question # 10

Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?

A.

TODAY + 1bm

B.

TODAY + 1m

C.

CURRENTDATE + 4w

Page: 1 / 3
Total 28 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 26 May 2026