Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 1
Total 10 questions
Exam Code: ACD300                Update: Jul 8, 2025
Exam Name: Appian Certified Lead Developer

Appian Appian Certified Lead Developer ACD300 Exam Dumps: Updated Questions & Answers (July 2025)

Question # 1

You are planning a strategy around data volume testing for an Appian application that queries and writes to MySQL database.

You have administrator access to the Appian application and to the database.

What are two key considerations when designing a data volume testing strategy?

A.

Data from previous tests needs to remain in the testing environment prior to loading prepopulated data

B.

large datasets must be loaded via Applan processes

C.

The amount of data that needs to be populated should be determined by the project sponsor and the stakeholders based on their estimation

D.

Testing with the correct amount of data should be in the definition of done as part of each sprint.

E.

Data model changes must wait until towards the end of the protect.

Question # 2

You are just starting with a new team that has been working together on an application for months. They ask you toreview some of their views thathave been degrading inperformance. The viewsare highly complex with hundreds of lines of SOL

What is the first step in troubleshooting the degradation?

A.

Go through the entire database structure to obtain on overview, ensure you understand the business needs, andthen normalize the tables to optimizeperformance.

B.

Run an explain statement on the views, identify criticalareas of improvement that can be remediated and without business knowledge

C.

Go through all of the tables one by one to identify which of the grouped by. ordered by. or joined keys are currently indexed

D.

Browse through the tables, note any tables that contain a large volume of null values, and work with your team to plan for table restructure.

Question # 3

You have an active development team (Team A) building enhancements for an application (App X'). and ate currently using the TEST environment for UAT.

A separate operations team ('Team B) discovers a critical error in the Production instance of App X that they must remediate However. Team 6 does not have a hotfix stream for which to accomplish this The available environments are DEV. TEST, and PROD

Which risk mitigation effort should both teams employ to ensure Team AS capital project is only minorly interrupted, and Team B s critical fix can be completed and deployed quickly to end users?

A.

Team 8 must communicate to Team A which component will be addressed in the hotfix to avoid overlap of changes It overlap exists, the component must be versioned to its PROD state before being remediated and deployed, and then versioned back to its latest development state If overlap does not exist, the component may be remediated and deployed without any version changes

B.

Team A must analyze their current codebase in OEV lo merge the hotfix changes into their latest enhancements. Team B is then requited to wait for the hotfix to follow regular deployment protocols from DEV to the PROO environment.

C.

Team 8 must address changes in the TEST environment These changes can then be tested and deployed directly to PROD. Once the deployment is complete. Team B can then communicate their changes to Teams to ensure they are Incorporated as a part of the next release.

D.

Team 8 must address the changes directly in PROD. As there is no hotfix stream, and OEV and TEST are being utilized for active development it is best to avoid a conflict of components. Once Team A has completed their enhancements work. Team 6 can update DEV and TEST accordingly.

Question # 4

What are two advantages of having High Availability (HA) for Applan Cloud applications?

A.

An Applan Cloud HA instance is composed of multiple active nodes running in different availability zones in differentregions.

B.

Data andtransactions are continuouslyreplicated across the active nodes to achieve redundancy and avoid single points offailure.

C.

A typical Appian Cloud HA instance is composed of two active nodes.

D.

In the event of a system failure, your Appian instance will fie restored and available to your users in less than 15 minutes.having lost no more than the last 1minute worth of data.

Question # 5

You are required to configure a connection so that Jira can inform Appian when specific tickets change (using webhook).

Which three required steps will allow you to connect both systems?

A.

Create a Web API object and set up the correct security.

B.

Configure the connection In Jira specifying the URE and credentials

C.

Create a new API Key and associate a service account

D.

Give the service account system administrator privileges

E.

Create an integration object from Applan to Jira to periodically check the ticket status

Question # 6

You are designing a process that is anticipated to be executed multiple times a day. This process retrieves data from an external system and then calls various utility processes as needed. The mam process will not use the results of the utility processes, and there are no user forms anywhere.

Which design choice should be used to start the utility processes and minimize the load on the execution engines?

A.

Use the Start Process Smart Service to start the utility processes.

B.

Start the utility processes via a subprocess synchronously.

C.

Use Process Messaging lo star! the utility process.

D.

Start the utility processes via a subprocess asynchronously

Question # 7

Your Appian project just went live with the following environment setup; DEV > TEST (SIT/DAT) > PROD

Your client is considering adding a support team to manage production defects and minor enhancements, white the original development team focuses on Phase 2 Your client is asking you for a new environment strategy that will have the least impact on Phase 2 development work.

Which option involves the lowest additional server cost and the least code retrofit effort?

A.

Phase 2 development work steam: DEV > TEST (SIT) > STAGE (UAT) > PROO

Production support work stream DEV > TEST2 (SIT/UAT)>PROO

B.

Phase 2 development work Stream: DEV > TEST (SIT) > STAGE (UAT) > PROO

Production support work stream DEV2 > STAGE (S1T/UAT) > PROD

C.

Phase 2 development work stream: DEV > TEST (SIT/UAT) >PROD

Production support work stream DEV > TEST2 (SIT/UAT) > PROO

D.

Phase 2 development work stream: OEV > TEST (Srr/DAT) > PROO

Production support work stream. DEV2 > TEST (SIT/UAT) > PROD

Question # 8

You are taking your package from the source environment and importing it into the target environment.

Review the errors encountered during inspection:

Whatis the first action you should take to Investigate the issue?

A.

Check whether the object(UUIDending in 18028821) is included in this package

B.

Check whether the object(UUD ending in 7t00000i4e7a)is included in this package

C.

Check whether the object (UUID ending in 25606) is included in this package

D.

Check whether the object (UUID ending in 18028931) is included in this package

Question # 9

You add an index on the searched field of a MySQL table with many rows (>100k).

The field would benefit greatly from the Index in which three scenarios?

A.

The field contains a textual shot Business code.

B.

The field contains long unstructured text such as a hash

C.

The field contains many datetimes, covering a large range

D.

The Add contains Dig integers, above and below 0.

E.

The field contains a structured JSON.

Question # 10

You are taskedto build a large scale acquisition application for a prominent customer. The acquisition process tracks the time it takes is fulfill a purchase request with an award.

The customer has structured the contract so that there are multiple application dev teams.

How should you design for multiple processes and forms, while minimizing repeated code?

A.

Create a Center of Excellence (CoE)

B.

Create a common objects application.

C.

Create a Scrum of Scrums sprint meeting for the team leads

D.

Create duplicate processes and forms as needed

Page: 1 / 1
Total 10 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 16 Jul 2025