Weekend Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 9
Total 86 questions
Exam Code: RCDDv14                Update: Sep 13, 2025
Exam Name: BICSI Registered Communications Distribution Designer – RCDDv14

BICSI BICSI Registered Communications Distribution Designer – RCDDv14 RCDDv14 Exam Dumps: Updated Questions & Answers (September 2025)

Question # 1

A company hires a program manager to create a healthcare management system. After five months the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.

The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?

A.

Critical success factors

B.

Key performance indicators

C.

Benefits management plan

D.

Stakeholder engagement plan

Question # 2

Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)

A.

Test reports

B.

Shop drawings

C.

Cost summary

D.

Site survey

E.

Request for information (RFI)

Question # 3

A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete

What should the program manager do to understand the financial environment?

A.

Map costs to the expected benefits realization

B.

Establish intermediate budget based on historical information

C.

Establish program financial framework

D.

Obtain intermediate funding from the executive sponsor

Question # 4

The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

A.

Program management performance variances business criteria reweighting, root cause identification, and statistical sampling

B.

Interviewing, SWOT analysis, run chart and matrix-based charts

C.

Earned value management financial reporting systems, performance measurement techniques and program management information systems

D.

Delphi technique, scatter diagram. Pareto chart, and organization charts

Question # 5

During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

A.

cost projections.

B OSHA specifications

B.

client requirements

C.

equipment availability

Question # 6

Which of the following is the process of limiting fire and smoke using fire-resistive barriers?

A.

Detection

B.

Compart mentation

C.

Suppression

D.

Prevention

Question # 7

The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager must prepare the cash flow analysis

Which of the following should be considered to get a baseline budget?

A.

Currency exchange rates

B.

Component cost estimates

C.

Baseline schedule

D.

Program payment schedules

Question # 8

What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?

A.

300 mm (12 in)

B.

450 mm (18 in)

C.

610 mm (24 in)

D.

914 mm (36 in)

E.

2.4 m (8 ft)

Question # 9

An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

A.

0.006 m2 (8 in2)

B.

0.008 m2 (12 in2)

C.

0.040 m2 (60 in3)

D.

0.60 m2 (80 in3)

Question # 10

Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.

Page: 1 / 9
Total 86 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 13 Sep 2025