Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 14
Total 134 questions
Exam Code: PK0-005                Update: Jun 24, 2026
Exam Name: CompTIA Project+ Certification (2026)

CompTIA CompTIA Project+ Certification (2026) PK0-005 Exam Dumps: Updated Questions & Answers (June 2026)

Question # 1

A project team is running into challenges because members are unclear about other members' roles. Which of the following charts should the project manager create?

A.

Project plan

B.

Project road map

C.

Project milestone

D.

Project organizational

Question # 2

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Question # 3

Which of the following is the main reason for documenting artifacts?

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Question # 4

Which of the following would be considered operational security?

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Question # 5

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Question # 6

Which of the following activities are important parts of the closing phase? (Select two).

A.

Releasing resources

B.

Locking risks

C.

Updating stakeholder register

D.

Closing contracts

E.

Completing the work breakdown structure

F.

Negotiating the next project

Question # 7

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

A.

Removing access

B.

Closing contracts

C.

Project sign-off

D.

Project evaluation

Question # 8

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Question # 9

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

A.

Establish communication channels

B.

Plan a kickoff meeting

C.

Develop a responsibility assignment matrix

D.

Identify the stakeholders

Question # 10

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Page: 1 / 14
Total 134 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 24 Jun 2026