Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 3
Total 30 questions
Exam Code: CCM                Update: Oct 16, 2025
Exam Name: Certified Contract Manager

FIDIC Certified Contract Manager CCM Exam Dumps: Updated Questions & Answers (October 2025)

Question # 1

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

A.

The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.

B.

The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.

C.

The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.

D.

The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.

Question # 2

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

A.

True

B.

False

Question # 3

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?

A.

True

B.

False

Question # 4

Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

A.

A description of the varied work.

B.

A description of the proposed design.

C.

Details of the resources and methods to be adopted by the Contractor.

D.

A Programme for execution of the varied work.

Question # 5

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.

A.

True

B.

False

Question # 6

Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?

A.

True

B.

False

Question # 7

Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?

A.

The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).

B.

The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.

C.

Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.

Question # 8

Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?

A.

The concentration on dispute avoidance, including an enhanced role for the Dispute Avoidance and Adjudication Board (DAAB) in this respect, and promoting cooperation between the parties during the project.

B.

New procedures requiring the Contractor to prepare and implement a Quality Management System to show compliance with the Contract requirements.

C.

A fair and balanced approach where risk is allocated to the Party that is best able to bear and control that risk.

D.

New procedures requiring the Contractor to prepare and implement a Compliance Verification System to show that the design, materials, workmanship and certain other matters all comply.

Question # 9

The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

A.

The Commencement Date

B.

The date of the Taking Over Certificate

C.

The date on which the entire advance payment is repaid as stated in the Payment Certificate

D.

The date on which an amount is repaid by the Contractor as stated in the Payment Certificates

Question # 10

Which one of the following statements best describes the requirements of Time for Completion?

A.

This is the Contractor's fundamental time-related obligation, namely completion the whole of the Works within the Time for Completion calculated from the Commencement Date.

B.

This is the Contractor's fundamental time-related obligation, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

C.

This is one of the Contractor's obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

D.

This is one of the Contractor's obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Effective Date.

Page: 1 / 3
Total 30 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 16 Oct 2025