Pre-Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 5
Total 42 questions
Exam Code: CCM                Update: Apr 20, 2026
Exam Name: Certified Contract Manager

FIDIC Certified Contract Manager CCM Exam Dumps: Updated Questions & Answers (April 2026)

Question # 1

Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?

A.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

B.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

C.

A disproportionate amount of risks is allocated to the Contractor under the General Conditions.

D.

The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer ' s Requirements.

Question # 2

(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

A.

The Employer shall give a Notice to the Engineer, describing the event or circumstance giving rise to the cost, loss, delay or extension of the Defects Notification Period for which the Claim is made.

B.

The Notice shall be given to the Engineer, as soon as practicable, and no later than 28 days after the claiming Party became aware, or should have become aware, of the event or circumstance.

C.

A Notice from the Employer is not required in order to give a Notice to the Engineer for services requested by the Contractor.

D.

The Notice given by the Employer must also include the legal or contractual basis of the claim, including the clause of the Contract under which it is made.

Question # 3

Which of the following form a Contractor ' s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

Question # 4

Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?

A.

The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

All key delivery dates of Plant and Materials.

Question # 5

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

A.

True

B.

False

Question # 6

(Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?)

A.

Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer’s Requirements very well to see if the Works can be built on that location according to the Employer’s Requirements.

B.

Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer’s Requirements very thoroughly after the contract closes and see if the Employer’s Requirements is complete or if something is missing.

C.

Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999; in both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer’s Requirements very thoroughly and check on any errors, omissions or conflicts.

D.

Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after the contract close to report on any errors, mistakes or conflicts in the Employer’s Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; the Contractor has to review and verify the Employer’s Requirements more strictly before submitting the tender.

Question # 7

Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?

A.

True

B.

False

Question # 8

(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)

A.

You compliment the supervisor and ask him to excavate further and personally deliver the treasure to a university. No extension of time is granted.

B.

You thank the supervisor, secure the Site, instruct guarding measures, inform the Employer and authorities, and issue a Variation to cover the costs of protection measures.

C.

You inform the supervisor that a formal written notice under Sub-Clause 4.24 is required and no further instruction can be given until then.

D.

You instruct the supervisor to cover the finding and resume the Works immediately, and make a determination later.

Question # 9

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?

(Choose all correct answers — multiple possibilities)

A.

The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.

B.

The Employer is not bound by the Certificate issued by the Engineer.

C.

The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.

D.

If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer ' s entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.

Question # 10

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Page: 1 / 5
Total 42 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 20 Apr 2026