Question # 1

Below is the pseudo-code for the Win program:

The bingo program contains a data flow anomaly. Which data flow anomaly can be found in this program?

A.

Variable 'A" is not assigned a value before using it.

B.

Variable 'D" is defined but subsequently not used.

C.

The program does not contain any comments.

D.

It is recommended to use a variable instead of the hard-coded print results "Win" and *Loose".

Question # 2

BestFor Incorporated is a rapidly growing online financial services company that offers guidance to its customers on a range of financial products. Its first website, BestForMortgages, was launched two years ago, shortly followed by BestForPensions. The popularity of both sites has driven the company to expand its offerings into other sectors and a third website, BestForFood, is currently under development.

The first two websites have proven to be functionally robust but suffered from performance issues due to:

Underestimation of concurrent user access at peak times in its original operational profiles

Data volumes rapidly growing beyond expectations on a single database shared by both sites.

All three websites will share the same web server.

In consideration of the problems encountered with the first two websites, which TWO of the following types of testing should be performed on the BestForFood website to see whether similar defects exist?

A) Load Testing

B) Stress Testing

C) Scalability testing

D) Portability Testing

E) Recoverability testing

A.

a and c

B.

b and c

C.

b and d

D.

d and e

Question # 3

A new web site has been launched for a testing conference. There are a number of links to other related web sites for information purposes. Participants like the new site but complaints are being made that some (not all) of the links to other sites do not work.

Which type of test tool is most appropriate in helping to identify the causes of these failures?

A.

Review tool

B.

Hyperlink tool

C.

Static analysis tool

D.

Dynamic analysis tool

Question # 4

What is the common name for a type of automated testing technique that separates test input data and expected test results from the control script used to execute all of the tests?

A.

Data-based testing

B.

Keyword-driven testing

C.

Model-driven testing

D.

Behavior-based testing

Question # 5

Which of the following statements BEST describes how tools support model-based testing?

A.

Finite state machines are used to describe the intended execution-time behavior of a software-controlled system.

B.

Random sets of threads of execution are generated as test cases.

C.

Large sets of test cases are generated to provide full code coverage.

D.

An engine is provided that allows the user to execute the model.

Question # 6

Consider the following specification:

If you are flying with an economy ticket, there is a possibility that you may get upgraded to business class, especially if you hold a gold card in the airline’s frequent flier program. If you don’t hold a gold card, there is a possibility that you will get ‘bumped’ off the flight if it is full when you check in late.

This is shown in the control flow graph below. Note that each box (i.e., statement, decision) has been numbered.

Three tests have been run:

Test 1: Gold card holder who gets upgraded to business class

Test 2: Non-gold card holder who stays in economy

Test 3: A person who is bumped from the flight

What is the level of decision coverage achieved by these three tests?

A.

60%

B.

67%

C.

75%

D.

80%

Question # 7

Consider the pseudo code for the Price program:

Which of the following statements about the Price program describes a control flow anomaly to be found in the program?

A.

The Price program contains no control flow anomalies.

B.

The Price program contains unreachable code.

C.

The Price program contains data flow defects.

D.

The Price program contains an infinite loop.

Question # 8

You are defining the test approach for an Agile project developing a system to control traffic lights at busy road junctions. The system will use sensors to measure traffic density and flow rates, optimizing traffic flow. While safety-critical, a risk assessment has deemed the project's risk level as low due to the team's expertise.

Which option below represents the BEST test approach for this project?

Key to symbols:

    + (highly recommended)

    (recommended)

    o (neutral/optional)

    • (not recommended)

    - (not to be used)

SELECT ONE OPTION

A.

3

B.

4

C.

2

D.

1

Question # 9

Why could test cases need to be refactored in an Agile project?

SELECT ONE OPTION

A.

To maintain bi-directional traceability with the user stories

B.

To increase the breadth of black box coverage

C.

To make them easier to understand and cheaper to modify

D.

To ensure that the tests and code remained aligned

Question # 10

Consider the following fault attack:

• Force all possible incoming errors from the software/operating system interfaces to the application.

Which of the following is the kind of failure you are looking for when using this attack?

A.

Application crashes when unsupported characters are pasted into an input field.

B.

Application crashes when the network is unavailable.

C.

Application crashes due to a lack of portability.

D.

Application miscalculates total monthly balance due on credit cards.

Page: 1 / 6
Total 52 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 16 Oct 2025