Cyber Monday Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 13
Total 121 questions
Exam Code: ISTQB-CTFL                Update: Dec 5, 2025
Exam Name: ISTQB Certified Tester Foundation Level (CTFL v4.0)

ISTQB ISTQB Certified Tester Foundation Level (CTFL v4.0) ISTQB-CTFL Exam Dumps: Updated Questions & Answers (December 2025)

Question # 1

Which one of the following statements relating to the benefits of static testing is NOT correct?

A.

Static testing enables early detection of defects before dynamic testing is performed.

B.

Static testing reduces testing costs and time.

C.

Static testing increases development costs and time.

D.

Static testing identifies defects which are not easily found by dynamic testing.

Question # 2

The following incident report that was generated during test of a web application.

What would you suggest as the most important report improvement?

Defect detected date: 15 8.2010

Defect detected by: Joe Smith

Test level System test

Test case: Area 5/TC 98

Build version: 2011-16.2

Defect description After having filled out all required fields in screen 1, t click ENTER to continue to screen 2 Nothing happens, no system response at all.

A.

Add information about which web browser was used

B.

Add information about which developer should fix the bug

C.

Add the time stamp when the incident happened

D.

Add an impact analysis

Question # 3

Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?

A.

Test-Driven Development (TDD)

B.

Acceptance Test-Driven Development (ATDD)

C.

Behavior-Driven Development (BDD)

D.

Domain-Driven Design (DDD)

Question # 4

Which one of the following is a typical entry criteria for testing?

A.

Planned tests have been executed.

B.

Availability of testable requirements.

C.

The number of unresolved defects is within an agreed limit.

D.

The number of estimated remaining defects is sufficiently low.

Question # 5

Which of the following statements about how different types of test tools support testers is true?

A.

The support offered by a test data preparation tool is often leveraged by testers to run automated regression test suites

B.

The support offered by a performance testing tool is often leveraged by testers to run load tests

C.

The support offered by a bug prediction tool is often used by testers to track the bugs they found

D.

The support offered by a continuous integration tool is often leveraged by testers to automatically generate test cases from a model

Question # 6

Which of the following statements about the test pyramid is TRUE?

A.

Each layer of the test pyramid groups tests related to a single non-functional quality charactenstic.

B.

The higher the layer of the test pyramid, the more production code a single automated test within the layer tends to cover

C.

The higher the layer of the test pyramid, the more maintainable a single automated test within the layer tends to be

D.

The higher the layer of the test pyramid, the more isolated a single automated test within the layer tends to be.

Question # 7

Which of the following tasks is MOST LIKELY to be performed by the tester?

A.

Develop a test strategy and test policy for the organization

B.

Promote and advocate the test team within the organization

C.

Create the detailed test execution schedule

D.

Introduce suitable metrics for measuring test progress

Question # 8

Metrics can be collected during and at the end of testing activities to assess which of the following?

i. Progress against the planned schedule and budget.

II. Current quality of the test object.

Hi. Adequacy of the test approach.

iv. Effectiveness of the test activities with respect to the objectives.

v. All the above.

Select the correct answer:

A.

Only i and ii.

B.

Only i and iii.

C.

Only I, ii and iv.

D.

Only v.

Question # 9

During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time.

The team agreed on the following:

1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra-large, and Extra-extra-large.

2. If estimation values differ significantly, the highest score will be used for estimation purposes.

The result of the first round of planning poker:

Team MemberEstimation

BusinessLarge

DevelopmentExtra-extra-large

TestingExtra-extra-large

Which of the following options best represent the team’s next actions?

A.

The fact that all estimations are high indicate that the user story is not well understood or should be broken down into multiple smaller stories.

B.

The pre-agreed rules state that the highest score should be used for estimation, resulting in the user story being categorised as Extra-extra-large.

C.

Since the business representative is likely to have the most informed view of the requirement, the user story is categorised as a Large.

D.

the team discusses the differences in the estimates and repeats the poker round until an agreemet is reached.

Question # 10

In order to exercise the right to vote, a person must meet the following requirements:

    be able to prove citizenship of the country

    be a resident in the administrative unit concerned

    have a minimum age of 18 years

    no other reasons for exclusion exist

Create the associated decision table and minimize it so that all conditions are correctly covered.

Hint: remember to use the "no other reasons for exclusion exist" condition when creating the decision table.

How many test cases are at least required to achieve the coverage of all decision rules and what could be the concrete test cases?

A.

5 test cases. 1 test case where all 4 prerequisites are fulfilled and 4 test cases for exactly one unfulfilled prerequisite each.

B.

16 test cases. With 4 conditions, each of which can be true or false, there are 16 (2 to the power of 4) possible combinations to be tested.

C.

2 test cases. 1 test case where all 4 conditions are fulfilled and 1 test case where all 4 conditions are not fulfilled.

D.

8 test cases. With 4 conditions, each of which can be true or false, there are 8 (4*2) possible combinations to be tested.

Page: 1 / 13
Total 121 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 05 Dec 2025