A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?
Which tool should a project manager use to calculate cost variance for a project?
Monte Carlo is which type of risk analysis technique?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
Which of the following factors is lowest at the start of the project?
Which is an output from Distribute Information?
Which cost estimate technique includes contingencies to account for cost uncertainty?
Which of the following reduces the probability of potential consequences of project risk events?
Which tool and technique is used in Conduct Procurements?
Which of the following tools and techniques is used in the Verify Scope process?
Which Process Group contains those processes performed to define a new project?
Which process occurs within the Monitoring and Controlling Process Group?
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
How is the schedule variance calculated using the earned value technique?
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
Documented identification of a flaw in a project component together with a recommendation is termed a:
Co-location is a tool and technique of:
What is the most accurate rough order of magnitude (ROM)?
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Testing falls into which of the following categories of cost of quality?
Which of the following are outputs of Develop Project Team?
Which is the correct formula for calculating expected activity cost for three-point estimating?
How many Project Management Process Groups are there?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which of the following is the primary output of the Identify Risks process?
What is a tool to improve team performance?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
What is the primary benefit of meeting quality requirements?
Which of the following is an output of Direct and Manage Project Execution?
Which of the following types of a dependency determination is used to define the sequence of activities?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
Which is used to solicit proposals from prospective sellers?
The precedence diagramming method (PDM) is also known as:
A tool or technique in Perform Quality Control that a project manager would use is:
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Which of the following events would result in a baseline update?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
Quality metrics are an output of which process?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
In which Project Management Process Group is the project charter developed?
Which of the following is a tool or technique of the Define Activities process?
Another name for an Ishikawa diagram is:
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
In which domain of project management would a Pareto chart provide useful information?
Which process involves identifying and documenting the logical relationships between project activities?