Pre-Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 8
Total 396 questions
Exam Code: CAPM                Update: May 30, 2026
Exam Name: Certified Associate in Project Management (CAPM)

PMI Certified Associate in Project Management (CAPM) CAPM Exam Dumps: Updated Questions & Answers (May 2026)

Question # 1

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Question # 2

What is project management?

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Question # 3

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.

What should the project manager do to address this issue?

A.

Apply emotional intelligence (El) skills, such as active listening, to understand the team ' s issues.

B.

Instruct the team members to self-organize and resolve any outstanding issues.

C.

Ask the team members to record their concerns in the lessons learned log for future action.

D.

Encourage the team to follow the project plan that was developed with team input.

Question # 4

With regard to a project manager ' s sphere of influence in a project, which of the following does the project manager influence most directly?

A.

Suppliers

B.

Customers

C.

Governing bodies

D.

Project team

Question # 5

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Question # 6

Agile release planning provides a high-level summary timeline of the release schedule based on.

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Question # 7

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Question # 8

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

Question # 9

Projects are separated into phases or subprojects; these phases include:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Question # 10

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?

A.

Risk management plan

B.

Communications management plan

C.

Change management plan

D.

Stakeholder engagement plan

Question # 11

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Question # 12

Which scenario is most desirable during the execution phase of a project?

A.

Apply and use quality controls to ensure expectations are met throughout the project

B.

Communicate quality failures to the sponsor for feedback

C.

Conduct all quality inspections at the end of the project

D.

Only correct quality issues found if it will keep you within the budget

Question # 13

Which type of graphic is displayed below?

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Question # 14

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Question # 15

Which project performance domain is the work breakdown structure (WBS) developed?

A.

Development approach and life cycle

B.

Delivery performance

C.

Project work

D.

Planning

Question # 16

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Question # 17

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Question # 18

The following is a network diagram for a project.

The total float for the project is how many days?

A.

5

B.

9

C.

12

D.

14

Question # 19

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

A.

Work performance information

B.

Bidder conferences

C.

Complexity of procurement

D.

Procurement management plan

Question # 20

What can the project manager find among the factors that could lead a project to be tailored

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

Question # 21

Plan Risk Management is the process of defining how to:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Question # 22

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Question # 23

Which statement is related to the project manager ' s sphere of influence at the organizational level?

A.

A project manager interacts with other project managers to detect common interests and impacts between their projects.

B.

A project manager facilitates communication between the suppliers and contractors on the project.

C.

A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.

D.

A project manager may inform other professionals about the value of project management.

Question # 24

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Question # 25

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

A.

improvement

B.

program

C.

result

D.

portfolio

Question # 26

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Question # 27

Which statement describes the relationship between Manage Quality process and Control process?

A.

Manage Quality is all about following planned processes and provedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.

B.

Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.

C.

Manage Quality and Control Quality are the same

D.

Manage Quality is part of Quality Management and Control is a subset of the Stakeholder Management Process group

Question # 28

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Question # 29

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

A.

Resource availability

B.

Infrastructure

C.

Academic research

D.

Corporate knowledge base

Question # 30

Reserve analysis is a tool and technique used in which process?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Question # 31

Stakeholder communication requirements should be included as a component of:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Question # 32

The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Question # 33

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Question # 34

A reward can only be effective if it is:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Question # 35

Project contracts generally fall into which of the following three broad categories?

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Question # 36

An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee ' s duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?

A.

Strategic

B.

Finance

C.

Project

D.

Operations

Question # 37

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Question # 38

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Question # 39

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Question # 40

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Question # 41

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Question # 42

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?

A.

Time and material (TandM)

B.

Cost plus fixed fee (CPFF)

C.

Fixed price

D.

Cost plus award fee (CPAF)

Question # 43

A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.

What should the project manager do next?

A.

Escalate this issue to the project sponsor.

B.

Reschedule the rollout to start with another business unit.

C.

Reschedule the rollout to include the new requirements.

D.

Escalate this issue to the project management office (PMO).

Question # 44

Who defines the scope of the product

A.

The client

B.

The project manager

C.

The team

D.

The program manager

Question # 45

A project manager is leading a project in a volatile industry. Industry standards are updated often, which requires the project team to make frequent adjustments to their work.

What should the project manager create to manage the possible changes?

A.

Communications management plan

B.

Cost management plan

C.

Risk management plan

D.

Quality management plan

Question # 46

A graphic display of project team members and their reporting relationships is known as a:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Question # 47

An output of the Develop Project Team process is:

A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Question # 48

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.

What are the four elements of a RACI chart?

A.

Recommend, approve, coordinate, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, accountable, consult, and inform

D.

Responsible, accountable, coordinate, and inform

Question # 49

Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?

A.

All business rules and data requirements for each process are documented.

B.

All relevant business rules for each process are documented.

C.

The resulting documentation adheres to established organizational standards.

D.

The data requirements for each process are documented.

Question # 50

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Page: 1 / 8
Total 396 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 30 May 2026