Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 8
Total 396 questions
Exam Code: CAPM                Update: Aug 28, 2026
Exam Name: Certified Associate in Project Management (CAPM)

PMI Certified Associate in Project Management (CAPM) CAPM Exam Dumps: Updated Questions & Answers (August 2026)

Question # 1

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Question # 2

What is the recommended approach for handling risk in a high-variability environment?

A.

Adaptive

B.

Predictive

C.

Iterative

D.

Incremental

Question # 3

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Question # 4

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Question # 5

An intentional activity to modify a nonconforming product or product component is called:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Question # 6

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Question # 7

An input of the Plan Procurement Management process is:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Question # 8

Completion of the product scope is measured against the product:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Question # 9

Which tool or technique is used in the Develop Project Management Plan process?

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Question # 10

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Question # 11

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

A.

Storyboarding

B.

Wireframes

C.

Data simulation

D.

Report prototyping

Question # 12

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Question # 13

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Question # 14

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

A.

Develop Schedule

B.

Create VVBS

C.

Estimate Activity Resources

D.

Define Scope

Question # 15

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Question # 16

Which is an output of the Collect Requirements process?

A.

Requirements traceability matrix

B.

Project scope statement

C.

WBS dictionary

D.

Work performance measurements

Question # 17

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

Question # 18

What is the project manager ' s responsibility in Project Integration Management?

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Question # 19

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

A.

Video conferencing

B.

Audio conferencing

C.

Shared portal

D.

Email/chat

Question # 20

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Question # 21

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Question # 22

Which tool should a project manager use to calculate cost variance for a project?

A.

Contingency analysis

B.

Review lessons learned from similar projects

C.

Expert judgment

D.

Actual cost

Question # 23

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Question # 24

Which of the following is a tool and technique used in the Develop Schedule process?

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Question # 25

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Question # 26

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Question # 27

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

A.

Interrelationship digraphs

B.

Tree diagram

C.

Affinity diagram

D.

Network diagram

Question # 28

What specific quality considerations should be examined while completing Quality Management plan?

A.

Risk registerB Stakeholder engagement

B.

Continuous improvement

C.

Standards and regulatory compliance

Question # 29

What does the creation of a project management plan accomplish?

A.

Defines the basis of all project work and how it will be performed

B.

Acknowledges the existence of a project and defines its high-level information

C.

Authorizes the project manager to apply organizational resources to project activities

D.

Provides the project manager with organizational standards, policies, processes, and procedures

Question # 30

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

A.

Analysis

B.

Appetite

C.

Tolerance

D.

Response

Question # 31

A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.

To reduce the risk with this approach, which step should the business analyst take?

A.

Add the risk to the risk register so other stakeholders are aware of the approach.

B.

Distribute the documented requirements to relevant stakeholders in all time zones for review and comment.

C.

Ask the stakeholders in the elicitation sessions to speak on behalf of stakeholders in other time zones.

D.

Request the project sponsor to approve this requirements elicitation approach for this project.

Question # 32

Which project documents can determine the budget?

A.

Procurement documents, contracts, requirements documentation, and basis of estimates

B.

Basis of estimates, cost estimates, project schedule, and risk register

C.

Business case, project charter, statement of work, and cost estimates

D.

Scope baseline, resource management plan, activity list, and assumption log

Question # 33

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Question # 34

Tools and techniques used for Plan Communications include the communication:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Question # 35

An input to the Perform Integrated Change Control process is:

A.

expert judgment

B.

seller proposals

C.

the project charter

D.

the project management plan

Question # 36

Project governance refers to framework.......which of the following is a portfolio?

Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?

A.

A portfolio is a group of projects, programs, subsidiary portfolios and operations managed together to achieve strategic objectives.

B.

A portfolio is the mam project of the company, supervised directly by the CEO.

C.

A portfolio is a group of projects managed by the same project manager.

D.

A portfolio is a group of related proiecls, programs, subsidary portfolios, and operation*, thai provides similar products or services.

Question # 37

Which of the following is an input to Control Scope?

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Question # 38

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Question # 39

What is an emerging practice in stakeholder engagement?

A.

Confirming that all identified stakeholders are engaged and actually affected by the work

B.

Assuring that team leadership is primarily involved in stakeholder engagement

C.

Ensuring that stakeholders do not change after stakeholder identification

D.

Ensuring that stakeholders most affected by the work are involved as collaborative team partners

Question # 40

In which Knowledge Area is the project charter developed?

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Question # 41

Tailoring considerations for project scope management may include:

A.

requirements management, stability of requirements, development approach, and validation and control.

B.

WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.

C.

business needs, product descriptions, project restrictions, and project management plan.

D.

issues defining and controlling what is included in the project, vended deliverables, and quality reports.

Question # 42

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Question # 43

During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?

A.

Bonuses based on accomplishment criteria

B.

New working contract with more benefits

C.

Promotion opportunities with this project

D.

Assignment of key roles and responsibilities

Question # 44

The key benefit of the Monitoring and Controlling Process Group is the ability to:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Question # 45

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Question # 46

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

A.

Look at the quality metrics.

B.

Validate the scope.

C.

Review the quality checklist.

D.

Conduct a quality audit.

Question # 47

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Question # 48

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

Question # 49

When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?

A.

Update the schedule baseline

B.

Review the schedule baseline

C.

Initiate a change request

D.

Update the risk register

Question # 50

After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?

A.

Ability to manage strategic goals across multiple projects

B.

Skills to manage a large project

C.

Competency to manage multiple projects that align departments

D.

Capability of managing project schedules

Page: 1 / 8
Total 396 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 28 Aug 2026