At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?
Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.
How should the project manager explain why this is not the forum to ask these questions?
A project team realizes that an important task on the iteration backlog will take more time than originally estimated What should the project team do?
A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"
How should the agile lead respond?
A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?
An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.
How should the agile coach address this change?
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?
After some iterations, the agile practitioner observes that the team is self-organizing in small knowledge silos. Which action should be taken regarding the team's behavior?
On what should an agile team work to achieve predictable flow?
On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?