Question # 1

A project team identifies a number of technical challenges with features in the next sprint.

What should they do?

A.

Request direction from the technical manager

B.

Encourage the Product Owner to reallocate the features to another sprint

C.

Determine who is best qualified to address the challenges

D.

Ask the Product Owner to assign the tasks to the most appropriately skilled resources

Question # 2

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team ' s historical velocity to calculate a range of features that can be delivered

Question # 3

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

A.

Prepare an effort estimation for each story based on their technical expertise.

B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.

Consider the possible risks of each selected user story and the value they add for the final user.

Question # 4

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

A.

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team ' s velocity.

B.

Prioritize the most valuable product features in the backlog first.

C.

Determine the features with the highest risk and release those first.

D.

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

Question # 5

What should the agile practitioner do?

A.

Select and implement collaboration tools to augment team interactions

B.

Provide each geographical area with their own product owner and divide the work between the teams

C.

Increase the number of requirements documents and ensure they are clearly communicated

D.

After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Question # 6

A team member has asked a question about the responsibilities of the Product Manager, QA, and the team regarding quality.

What should the Agile Project Manager advise?

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.

B.

The entire team is responsible for quality, but each team member ' s role may vary as stated in the definition of done (DoD).

C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.

D.

Quality is the responsibility of the entire team, and the Product Manager defines the functionality from end to end.

Question # 7

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Question # 8

The vice president (VP) of an organization has been asked by the chief information officer (CIO) to have their teams to embrace an agile approach to projects. The VP, however, often insists teams use a more predictive approach to project management which allows the project managers to do what they like.

How should an agile team member coach the VP and teams be more effective?

A.

Coach the chief information officer (CIO) on implementation of agile benefits and expectations.

B.

Coach the teams on implementation of agile benefits and expectations.

C.

Coach the managers on implementation of agile benefits and expectations.

D.

ICoach the vice president (VP) on implementation of agile benefits and expectations.

Question # 9

What should the Scrum Master mention at the next retrospective?

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

Question # 10

Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

A.

Raise an impediment that resource tasks will be blocked and notify the Product Owner

B.

Ask the delivery manager for a temporary resource

C.

Ask the Scrum Master to assign that team member ' s tasks to the next available resource

D.

Assume the team member ' s tasks to meet iteration goals and notify the Product Owner