Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 9
Total 86 questions
Exam Code: PMI-RMP                Update: Aug 28, 2026
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam

PMI PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Exam Dumps: Updated Questions & Answers (August 2026)

Question # 1

A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

What should the project manager do next to determine risk impact of assumptions and constraints?

A.

Add all assumptions and constraints to the risk register.

B.

Add the risk impact of the assumptions in the risk register.

C.

Add the assumptions and constraints to the assumption log.

D.

Add the assumptions and constraints in the project charter.

Question # 2

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

A.

Conduct a subject matter expert (SME) meeting.

B.

Perform qualitative analysis.

C.

Prioritize after quantitative analysis

D.

Prioritize the stakeholders affected.

Question # 3

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

Question # 4

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

A.

Update the new risk in the risk register.

B.

Plan responses for the new risk.

C.

Passively accept the new risk.

D.

Add the new risk to the watch list.

Question # 5

An international telecommunications company is preparing to launch a new service across multiple regions. The project team is concerned about the varied technical issues and regulatory challenges in each region. The risk manager is tasked with identifying and analyzing risks to prioritize them based on their potential impact.

Which two actions should the risk manager take? Choose two.

A.

Assign risks to the most tenured team members for assessment.

B.

Engage with local experts to understand region-specific constraints.

C.

Model one region and then follow the same strategy in all regions.

D.

Apply a common risk matrix across all regions.

E.

Develop a customized risk matrix for each region.

Question # 6

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Question # 7

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

A.

Time Series Analysis

B.

Regression Analysis

C.

Variance Analysis

D.

Monte Carlo Analysis 

Question # 8

A risk manager is facilitating a session to define a response to a critical risk. Stakeholders from several business units participate in the brainstorming, leading to a range of ideas for possible responses. However, the risk manager now needs to understand which solutions will be cost effective.

What should the risk manager do?

A.

Complete a comprehensive trend analysis.

B.

Validate assumptions and constraints analysis.

C.

Perform decision tree analysis.

D.

Conduct a variance analysis.

Question # 9

A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.

Which approach should the risk manager take to improve the quality of the project risk analysis?

A.

Use brainstorming to identify more possible risks.

B.

Use a Monte Carlo simulation to identify risks.

C.

Use a work breakdown structure (WBS) to help analyze risks.

D.

Use a qualitative or quantitative analysis to analyze identified risks.

Question # 10

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Page: 1 / 9
Total 86 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 28 Aug 2026