Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 11
Total 510 questions
Exam Code: PMP                Update: Jul 14, 2025
Exam Name: Project Management Professional (2025 Version)

PMI Project Management Professional (2025 Version) PMP Exam Dumps: Updated Questions & Answers (July 2025)

Question # 1

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Question # 2

A project manager has been assigned with initiating a large project to deliver

complex equipment. Part of the project will be the result of a long research process, but once

this is completed, the other part of the project must be incrementally delivered to the

customer.

Which approach should the project manager choose for this project?

A.

Agile

B.

Waterfall

C.

Predictive

D.

Hybrid

Question # 3

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet

B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine

C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers

D.

Meet with the key stakeholders to identify the proper product concept for the development team

Question # 4

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

A.

Provide mentoring for the key team members on agile practices and support the team

with training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rules

stated in the document.

C.

Replace the key team members with new resources who are already aware of the agile

mindset.

D.

Provide directions to the team members on how to accelerate the company's

transformation, bringing the project back on track.

Question # 5

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Question # 6

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

A.

Assessed the technical and organizational readiness for the project and identified risks

at the beginning of the first iteration

B.

Requested the product owner's approval to add an external expert to define the

acceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with the

project

D.

Increased the communications between the team member and the product owner

Question # 7

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

Question # 8

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Question # 9

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Question # 10

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Question # 11

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Question # 12

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Question # 13

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

Question # 14

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Question # 15

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.

Question # 16

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

A.

US$650,000

B.

US$452,500

C.

US$547,500

D.

US$582,500

Question # 17

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Question # 18

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal and

external resource requirements.

B.

Commit each team member's time and deliverables and aim for overall project

completion.

C.

Continue the project implementation without the site engineers to ensure the schedule

is maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Question # 19

A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?

A.

Identify and escalate any identified risks to the facilitator to handle

B.

Update the risk register during every iteration with any open concerns

C.

Use regular feedback loops through daily standups iteration demos and retrospectives

D.

Focus on developing a working deliverable instead of documenting risks

Question # 20

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Question # 21

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Question # 22

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Question # 23

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

A.

Put the new requirements in the backlog with high priority and implement the

requested changes.

B.

Put the new requirements in the backlog and submit a formal change request for

approval.

C.

Put the new requirements in the backlog and let the product owner check their value

and priority.

D.

Put the new requirements in the backlog with low priority and implement the requested

changes.

Question # 24

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Question # 25

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?

A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.

B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country

C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.

D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.

Question # 26

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

A.

Share unsuccessful results from previous projects with a similar scope

B.

Provide the failed test results along with the agreed-upon acceptance criteria

C.

Show that the acceptance criteria were changed by the vendor without approval.

D.

Document in the risk log that the issues in the system were already identified

Question # 27

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback'?

A.

Assessed and analyzed personality indicators from the project team

B.

Sent the activity details to everyone involved prior to the session

C.

Communicated the decision to conduct this activity to the key team stakeholders

D.

Selected a vendor for the activity according to the procurement management plan

Question # 28

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders to

participate.

C.

Ensure that lessons learned are considered as part of the project schedule

decomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on other

projects.

Question # 29

A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?

A.

Include the issue in the risk register and update the team

B.

Document the continuing issue and failed solution

C.

Inform the stakeholders about the failure and update the issue log

D.

Meet with the project team to find another solution

Question # 30

A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.

Why did this action occur?

A.

Inadequate funds for the automation project

B.

Inadequate engagement of the political stakeholders

C.

Lack of competence to manage the automation project

D.

Lack of a proper legal framework in place

Question # 31

In a hybrid project, 100 new base stations are being added to a 4G mobile network

every month. At the end of the first month, the team is behind the target and the operator is

losing money. The stakeholders are requesting information on when the base stations can go

live and begin to bill.

What should the project manager do to take the schedule back and accelerate the return on

investment (ROI) of the project?

A.

Change the project approach to predictive.

B.

Increase reporting to the business.

C.

Clarify the agile and predictive modules.

D.

Reconsider necessary schedule reserves.

Question # 32

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

A.

Ensure that the whole team is appropriately recognized and organize a project farewell

party to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and save

them in the organization's project management information system (PMIS).

C.

Archive all the project documents following the organization's accepted practices so

the documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult to

undertake because the current project is not yet complete.

Question # 33

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Question # 34

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Question # 35

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Question # 36

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

A.

Recommend agile training programs that best suit the client project manager's schedule.

B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

D.

Provide the client project manager with agile best practice documents and web resources.

Question # 37

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

A.

Ensure all three teams deliver independently without interactions so that they remain

focused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern of

handing off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issues

between the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any other

unforeseen risks that might prevent progress.

Question # 38

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

A.

Perform collaborative work that is coordinated by the project manager.

B.

Rely on the expert judgment of the product owner.

C.

Use a market-based strategy.

D.

Engage the project sponsor.

Question # 39

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

Question # 40

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?

A.

Request a replacement for those team members who are unhappy with this way of

working.

B.

Schedule a session with the product owner to explain that no support items can be

taken into the sprints going forward.

C.

Ask human resources (HR) to send the team members to a change management

workshop.

D.

Schedule a session with the team to discuss the issues and work with them to define a

plan to manage the sprints going forward.

Question # 41

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Question # 42

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Question # 43

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

Question # 44

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

Question # 45

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

A.

Contract negotiation

B.

Team assessment

C.

Mentoring and coaching

D.

On-the-job training

Question # 46

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

Question # 47

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

Question # 48

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

Question # 49

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Question # 50

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Page: 1 / 11
Total 510 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 16 Jul 2025