Black Friday Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Page: 1 / 13
Total 612 questions
Exam Code: PMP                Update: Nov 30, 2025
Exam Name: Project Management Professional (2025 Version)

PMI Project Management Professional (2025 Version) PMP Exam Dumps: Updated Questions & Answers (November 2025)

Question # 1

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.

Update the communications management plan and implement the change

C.

Meet with the project sponsor to discuss how to address the situation.

D.

Meet with the stakeholder prior to the meeting to obtain their opinion

Question # 2

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Question # 3

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Question # 4

A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project

What should the project manager have the project team update to ensure proper communications to stakeholders?

A.

Project management plan

B.

Stakeholder engagement plan

C.

Stakeholder register

D.

Communications management plan

Question # 5

An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?

A.

Reschedule the project until the local travel restrictions are lifted.

B.

Schedule virtual sessions with the specialist to guide the team in completing the activity.

C.

Seek additional budget to train the project team on the required skill set.

D.

Refer to the organization's lessons learned repository and find an alternative solution.

Question # 6

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.

What should the project manager do?

A.

Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority

B.

Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities share this with all stakeholders, and ask the team to complete their tasks as scheduled

C.

Conduct a general meeting with all stakeholders and review and address a list of activities for each of them

D.

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities

Question # 7

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

A.

Team A as they have calculated fewer story points than team B.

B.

Team B as they have calculated more story points than team A

C.

The team that completes the most stories selected from the sprint backlog

D.

The team with the least amount of defects in their deliverables

Question # 8

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Question # 9

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

Question # 10

A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.

What should the project manager do next?

A.

Update the product backlog item with this new requirement.

B.

Escalate the issue of project impact to the project sponsor.

C.

Escalate the issue of project impact to the product owner.

D.

Update the stakeholder register to include the requirement owner.

Question # 11

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Question # 12

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)

A.

Define team ground rules

B.

Perform a retrospective session

C.

Implement daily team meetings.

D.

Request a manager performance review

E.

Conduct an annual review.

Question # 13

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Question # 14

A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again

What should the project lead do next?

A.

Notify senior management of the issues and have them review the importance of agreements with the team

B.

Challenge the team to determine if the issues surfaced again because agreements were not followed

C.

Post the agreements in a conspicuous place where all of the team members can see them.

D.

Let the team self-organize and determine the best means to prevent the issues from occurring again

Question # 15

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

A.

Check the approved list of requirements to see if there are any missing items.

B.

Work with the stakeholder to improve the requirements' acceptance criteria

C.

Review the requirements traceability matrix with the concerned stakeholder

D.

Discuss with the stakeholder which additional requirements should be added

Question # 16

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

A.

Review lessons learned from previous projects that used the same team

B.

Review the organizational culture, structure, and governance

C.

Coordinate a meeting to understand the situation and resolve any conflicts.

D.

Coordinate a meeting with regional managers to ask for support

Question # 17

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Question # 18

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

A.

Requested that the sponsor approved the change request first.

B.

Assessed the change's overall impact to the project before submission

C.

Ensured that the change request was aligned with the project scope

D.

Submitted the change request directly to the CCB

Question # 19

A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

Question # 20

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?

A.

Review the set of responsibilities with the team member

B.

Avoid the team member to prevent further conflicts

C.

Escalate the situation to the project sponsor

D.

Review the personnel skill documents

Question # 21

A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project

What should the project manager do to assist the new team member?

A.

Advise the new team member to enroll in project management training.

B.

Instruct the new team member to review the responsible, accountable consult, and inform (RACI) matrix before asking for help

C.

Advise the new team member to review the project charter and stakeholder engagement plan.

D.

Review the resource management plan and provide mentoring to the new team member if necessary

Question # 22

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

A.

Add the competitor's functionalities to the product backlog to improve the product

B.

Ask the sponsor to add more people to the team

C.

Help the team to find a new approach to launch the product as soon as possible

D.

Ask the team to increase the velocity to launch the product as soon as possible

Question # 23

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.

Insist that test-driven development is implemented along with the automated testing

D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Question # 24

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?

A.

Four iterations

B.

One iteration

C.

Two iterations

D.

Three iterations

Question # 25

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register

What should the project manager do?

A.

Assign the documenting task to a project team member

B.

Ask the SME to document and capture the occurrence.

C.

Request the SME to wait until the project closure phase.

D.

Take ownership of documenting this information

Question # 26

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?

A.

Execute it as a Scrum project

B.

Execute it as a predictive project

C.

Execute it using the same approach as the reference project

D.

Execute it as a project with stage gates

Question # 27

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session

B.

Contact the project sponsor and request new team members who are familiar with adaptive projects

C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project

D.

Freeze the design stage and look for an external resource to run iterative design at extra cost

Question # 28

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Question # 29

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?

A.

Ask the team to include the compliance requirement in the current sprint and deliver it.

B.

Add the new compliance requirement to the backlog as the technical team does not have any capacity.

C.

Include the compliance lead in the stakeholders list and wait for the next status meeting

D.

Collaborate with the compliance team member to review and prioritize the requirement’s delivery

Question # 30

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

Question # 31

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

A.

Ask the team member to follow the approved communications management plan to communicate their issue

B.

Schedule a meeting with the concerned team member to review and update the issue log together

C.

Review the risk register with the team member to find the proper response action for this issue.

D.

Ask the team member to raise a change request to assess the issue in detail

Question # 32

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

Question # 33

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?

A.

Update the quality management plan for the overall project

B.

Ask the client to verify and accept the tasks that have been completed

C.

Close out the project tasks that have been completed

D.

Update the communications management plan for the overall project

Question # 34

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Question # 35

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

Question # 36

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.

B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly

C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties

D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer

Question # 37

A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint.

How should the project manager help the team resolve the issue?

A.

Direct the senior-most member to determine the scope on behalf of the team.

B.

Discuss this with the team and decide what the scope of the feature should be.

C.

Ask the team to log the story in the product backlog and move on to the next feature.

D.

Encourage the team to collaborate to resolve their understanding of the feature.

Question # 38

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

A.

Clarify project benefits with the sponsor.

B.

Identify the goal of each work product

C.

Perform integration testing of each release

D.

Include the entire project team in testing

Question # 39

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder

B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan

C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan

D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.

Question # 40

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Question # 41

A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)

A.

Complexity and the cost of development

B.

Industry trends and the technical approach

C.

Cost of delaying some features against business value

D.

Reusing components from another product

E.

Length of time each feature has been on the backlog

Question # 42

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan

B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels

C.

Consult the resource management plan for an appropriate response

D.

Continue with existing sprint plans to ensure some of the scope will be delivered

Question # 43

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?

A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.

B.

Stop crashing the schedule

C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators

D.

Use a resource-levelling technique

Question # 44

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Question # 45

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)

A.

Check the risk register for a prepared response to a resource being suddenly unavailable.

B.

Check if the team member's activities are sufficiently documented to facilitate handover

C.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected

D.

Reassign responsibilities across the remaining members using the available float for training.

E.

Obtain the project sponsors support to replace the team member on leave

Question # 46

The project schedule is falling behind and the project manager observes that the project team seems to be spending the majority of their time writing documentation instead of performing project tasks What should the project manager do to help ensure that the team focuses on project tasks?

A.

Assign a team member to handle the documentation activities.

B.

Coach the project team to complete the project documentation activities

C.

Review and adapt the appropriate project artifacts.

D.

Save all documentation activities until tire end of the project

Question # 47

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Question # 48

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible

What should the project manager use to identify the risks?

A.

An analysis of shared risks between parties

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Expert judgment

D.

A risk value assessment

Question # 49

An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework

What should the project manager do in this situation?

A.

Include impediment resolutions during daily standup meetings

B.

Perform a root cause analysis during the standup meetings

C.

Create a dedicated sprint to solve the obstacles with the team

D.

Promote collaboration to help remove the obstacles for the team

Question # 50

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

A.

Used communication tools, such as video conferencing so different offices could communicate.

B.

Learned more about how each team member prefers to communicate before assigning project work

C.

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.

Ensured that the project would be the highest priority for all team members

Page: 1 / 13
Total 612 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 30 Nov 2025