Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 15
Total 148 questions
Exam Code: PfMP                Update: Oct 15, 2025
Exam Name: Portfolio Management Professional (PfMP)

PMI Portfolio Management Professional (PfMP) PfMP Exam Dumps: Updated Questions & Answers (October 2025)

Question # 1

Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, change to reflect the portfolio new vision?

A.

Portfolio Strategic Plan

B.

Portfolio Management Plan

C.

Communication Management Plan

D.

Portfolio Roadmap

Question # 2

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. A major risk has recently occurred and the risk owner came to you asking advise on how to report it. what would you advise her?

A.

Portfolio Process Assets

B.

Risk Register

C.

Portfolio Organizational Assets

D.

Portfolio Reports

Question # 3

While defining the portfolio, the portfolio manager uses a set of evaluation criteria in order to generate a list of portfolio components for optimization and balancing. Which of the following is not an evaluation criteria?

A.

Technology capabilities and capacities

B.

Costs

C.

Benefits, financial and non-financial

D.

Customer

Question # 4

A big strategic change occurred at the organization level and has impacted multiple portfolios in the organization including yours. The sponsor has asked you to analyze the change and update the needed documents. You managed this change and are currently updating the Portfolio Management Plan. Which of the following are part of this update

A.

Portfolio Organizational Structure

B.

Communication and Performance Management

C.

Stakeholder Engagement

D.

All of the options

Question # 5

In identifying risks to then manage and control, as the portfolio manager you are consulting organizational process assets such as:

A.

Commercial data bases

B.

Lessons learned

C.

Knowledge bases

D.

Values

Question # 6

Assume you are putting together for the Portfolio Review Board several options for consideration of potential components and current components. You are using an approach with different probabilities to determine outcomes and EMV. Which of the following would you recommend realizing Components A and B are new, while C and D are in progress:

A.

Component A

B.

Component B

C.

Component C

D.

Component D

Question # 7

Following a recent portfolio health check, you noticed that your portfolio is not aligned with the strategic plan and actions should be taken to stop losing money. What should be your next course of action?

A.

Escalate to the executive management

B.

Update the Strategic Plan

C.

Escalate to Governance Board

D.

Escalate to sponsor directly

Question # 8

One of your team members who is particularly interested in becoming a portfolio manager has asked you what is the relation between the Portfolio roadmap and the Programs/Projects roadmaps? What should be your answer to him?

A.

Program and Project roadmaps may be included in the portfolio roadmap

B.

There is no relation whatsoever

C.

Program and Project roadmaps are more detailed and less strategically aligned

D.

Portfolio roadmaps are high level approaches for program and project roadmaps

Question # 9

You are currently creating portfolio scenarios (what-if analysis) by reviewing components against prioritization criteria and using analysis techniques (e.g., options analysis, risk analysis, SWOT analysis, financial analysis). You are doing this in order to

A.

Understand the strategic priorities

B.

Create a basis for decision making

C.

Evaluate and select viable options

D.

Provide a guiding framework to operationalize the organizational strategic goals and objectives

Question # 10

Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is incorporated in all process groups as well. As a portfolio manager, how do you map the risk management elements to process groups?

A.

Risk Planning (Defining) - Risk Assessment & Response (Aligning)

B.

Risk Assessment (Defining) - Risk Planning (Aligning) - Risk Response (Authorizing & Controlling)

C.

Risk Planning (Defining) - Risk Assessment (Aligning) - Risk Response (Authorizing & Controlling)

D.

Risk Planning (Defining) - Risk Assessment (Planning) - Risk Response (Authorizing & Controlling)

Page: 1 / 15
Total 148 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 15 Oct 2025