Question # 1

You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

A.

$400,498

B.

$521,345

C.

$505,620

D.

$385,450

Question # 2

A software company's program manager is conducting closing procedures for a program. At the last steering

committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

A.

Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program's status.

B.

Initiate knowledge transfer with the receiving organization, and establish the program integration management plan.

C.

Update the financial, stakeholder, and contract management plans, and archive them in the program information repository.

D.

Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organization.

Question # 3

A global financial system is being delivered by the program team to allow access from anywhere in the world. Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted to validate compliance with this new regulation. This event, which was not anticipated at this phase of the program, will generate additional work for the program team. This effort is not included in the current program roadmap and benefits delivery plan.

What immediate actions should the program manager take?

A.

Negotiate with the CEO in an attempt to avoid the audit

B.

De-scope the capabilities of the system to not allow access from abroad

C.

Accept the risk of the audit and continue the program as planned

D.

Assess the impact of the audit and potential remediation on the program

Question # 4

Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?

A.

A change to add additional funds to the program scope

B.

A change to reduce the program scope

C.

Anything that management demands

D.

A change to add additional time to the program schedule

Question # 5

A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?

A.

Program scope management plan

B.

Program governance plan

C.

Program scope statement

D.

Program work breakdown structure

Question # 6

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

A.

Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.

B.

Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.

C.

Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.

D.

Add the lack of skilled resources to facilitate the large number of change requests to the issue log.

Question # 7

A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?

A.

Negative stakeholder

B.

Positive stakeholder

C.

Key stakeholder

D.

Hurdle stakeholder

Question # 8

You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

A.

Program work breakdown structure

B.

Program work breakdown structure dictionary

C.

Program charter

D.

Program scope statement

Question # 9

Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?

A.

Risk management plan

B.

Program management plan

C.

Personnel records

D.

Training records

Question # 10

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.

What should be done with the identified potential risk?

A.

Incorporate it into the risk register and perform a thorough analysis.

B.

Mitigate the risk before it is incorporated into the risk management plan.

C.

Document the risk in the program transition plan and identify it as a potential issue.

D.

Document it in the issue log and immediately notify the steering committee.