Question # 1

During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.

Which practice is being applied through the ‘controlling a stage’ process?

A.

Business case

B.

Organization

C.

Plans

D.

Quality

Question # 2

While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

A.

Yes, because a stage boundary may be aligned with an important external decision point, such as a funding approval

B.

Yes, because every stage may end immediately after one specialist product has been completed and funding has been approved

C.

No, because stage length must be determined solely by the level of risk

D.

No, because stage length must be determined by the technical complexity of the work

Question # 3

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Question # 4

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.

No, because it is an exception which should be escalated in an exception report

Question # 5

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board

B.

Yes, because the project board should collect and review work-package progress directly from each delivery team

C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances

D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages

Question # 6

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

A.

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

Question # 7

A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.

Is this an appropriate application of the issues practice, and why?

A.

Yes, because the legislation may affect the resources available to deliver the project

B.

Yes, because external events must be managed outside the project’s agreed controls

C.

No, because legislation should be recorded after its full effect on delivery is known

D.

No, because external events are managed by the business rather than by the project team

Question # 8

A high-level requirement that the design should be consistent with its surroundings was recorded during ‘starting up a project’. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.

Which management product should be updated with this information?

A.

Project product description

B.

Work package

C.

Product flow diagram

D.

Project plan

Question # 9

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Question # 10

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.