Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 3
Total 22 questions
Exam Code: PSM-II                Update: Oct 16, 2025
Exam Name: Professional Scrum Master II

Scrum Professional Scrum Master II PSM-II Exam Dumps: Updated Questions & Answers (October 2025)

Question # 1

Marian is a product Owner working on a Scrum Team on a new release for her product. Based on the average velocity of the previous release Marian estimated the project to take seven Sprints. Average velocity In the previous release was thirteen completed units of work per Sprint Development is three Sprints underway, with tour more Sprints to go until the release.

Product Backlog has been stable.

Over the first three Sprints, the Developers report their average velocity is nine, while not having fully tested all the delivered functionality. The Developers estimate that the unfinished testing would have required of a Sprints time. The Developers believe that the required

velocity of thirteen is within their reach. What is the most effective way to recover?

(choose the best answer)

A.

The Developers set the open work aside to be performed in one or more release

Sprints. They remind Marian to find funding for enough Release Sprints in which this remaining work can be done. up to one release Sprint per three development Sprints may be required, It is Marian's responsibility to inform users and stakeholders Of the impact on the release date.

B.

Transparency needs to be restored by addng the undone work to the Product

Backlog. The Developers must figure out a way to deliver in the upcoming Sprintsa velocity of not only 13 units of new work, but also two additional points to catch up undone work. It is the Scrum Master's duty to assess whether such repair is possible. If not, the Scrum Master initiates a restart with a more reliable team Or cancels the project. The Scrum Maste

C.

In the next Sprints, the Developers keep making sure that all of the selected scope per Sprint is as done as possible, at least at the past level of 90%. In every Sprint the undone work of the previous Sprint is estimated and added to the Sprint Backlog. It comes on top of the expected forecast of 13 units, so it does not mess up progress on the product Backlog.

D.

The Developers inform Marian that the progress she has perceived to date is not correct The Increment is not releasable. They give Marian their estimate of the effort it would take to get the past work done, and suggest doing that work first before proceeding with new features. The Developers also re-estimate the effort to complete the remaining backlog, including all testing. In the end, it is Marian's call to continue the project or to ca

Question # 2

How does the Scrum Master serve the Scrum Team?

(choose the best two answers)

A.

The Scrum Master coaches the Scrum Team and the organization how to work empirically.

B.

The Scrum Master resolves every impediment that the Developers run into

C.

The Scrum Master never intervenes in matters of the Scrum Team, but allows

them to maximize their autonomy and freedom.

D.

The Scrum Master facilitates Scrum events as requested or needed

Question # 3

Self-management is more effective when it happens within boundaries.

Select two relevant boundaries for self-management provided by the Scrum framework.

(choose the best two answers)

A.

Timeboxing work to allow for frequent inspection.

B.

Clearly defining sub-responsibilities and handovers within the Scrum Team.

C.

Creating a valuable and useful Increment by the end of each Sprint.

D.

Having an even number of members in a Scrum Team to be able to do pair programming and be more productive.

Question # 4

What are two signs that a Scrum Team is self-managing?

(choose the best two answers)

A.

Management understands the team's daily tasks at all times.

B.

The Developers always know the status of the assigned work needed to deliver

the tasks committed in the Sprint Plan.

C.

The Scrum Team can resolve conflicts and continue working.

D.

Creativity flourishes and new possibilities are explored.

Question # 5

You are the Scrum Master for a Scrum Team whose Daily Scrum is scheduled to start at 10:00 each day. Developers routinely turn up late, and once everyone has assembled, the Daily Scrum starts. By then it is typically 4 to 5 minutes later than scheduled. Other meetings in the organization typically allow 4 to 5 minutes for people to transport within the building.

Some Developers complain that it is now hard to achieve the purpose of the Daily Scrum within the timebox, since there is only 10 or 11 minutes left after waiting for people to show up. The Developers ask for your advice.

(choose the best answer)

A.

You suggest an experiment: moving the event to a time that better suits the team.

B.

You escalate this issue to management since you are responsible for ensuring Scrum is understood and enacted.

C.

To incentivize showing up on time, you tell the Developers that when people come late to the Daily Scrum, they will pay a small fee.

D.

You turn the question back to the Developers and ask what they think should be done to ensure their Daily Scrum is effective and meets its purpose.

E.

You suggest that when someone shows up late they cannot join that day's Daily

Scrum.

Question # 6

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product The stakeholder is unhappy with the slow performance, a complaint that the Product Owner agreeswithAs the Scrum Master how will you move this forward?

(choose the best answer)

A.

Encourage the Product Owner to bring the performance concerns to the rest of the Scrum Team and work together to improve the Definition of Done

B.

Wait to bring this up in the next Sprint Retrospective as this is the appropriate time for the Developers to re-consider the Definition of Done.

C.

Bring the concern to the quality assurance members of the Scrum Team and ask them to improve how the system is tested.

D.

Explain to the Product Owner that it is up to the Developers to decide on acceptable performance standards as they own the Definition of Done

Question # 7

Which of the following affect the outcome of a Sprint?

(choose all that apply)

A.

The complexity of the problem being solved.

B.

The complexity of the requirements.

C.

The skills and working relationships of the people on the Scrum Team(s).

Question # 8

The Developers are waiting for an external supplier to deliver a specific product component that they need to integrate and use. Without that component there will not be enough work in the next Sprint to occupy the full team. They ask their Product Owner to re-order the Product Backlog. The Product Owner asks the Scrum Master for help. What would be good advice for the Product Owner?

(choose the best answer)

A.

Tell the Product Owner that the Product Backlog needs to be re-ordered to maximize utilization of the Developers. It is important to keep productivity high through proper use of the capacity available

B.

Tell the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog. Timeline of the flow might be influenced by such dependencies and require some level of Product Backlog re-ordering

C.

Tell the Product Owner to remove all work involving the external component from the Product Backlog and create a new backlog for it. The work can then be planned in one or more separate Sprints as soon as the component is available.

Question # 9

Which statements are true about the Sprint Goal?

(choose the best two answers)

A.

Sprint Goals often change during the Sprint as new insights emerge during the work.

B.

During Sprint Planning, the Scrum Team crafts a Sprint Goal based on anobjective that the Product Owner would like to achieve that Sprint.

C.

Sprint Goals give Developers flexibility and creativity on how to implement functionality during the Sprint

D.

The use of Sprint Goals is optional in the Scrum Framework

Question # 10

Another team's Scrum Master seeks your advice. The Daily Scrum always runs longer than 15 minutes. The Developers suggest splitting the Scrum Team into two teams. What is your response?

(choose the best answer)

A.

You disagree — there is not enough information to justify splitting a team into two teams. You ask if there is anything you can do to help your colleague, for example observe one of the Daily Scrums with them.

B.

You agree - this is an appropriate solution to the problem.

C.

You disagree - you tell the Scrum Master that as Scrum Master they need to manage the timebox better.

D.

You agree - splitting the team into two teams is a good strategy to allow them to learn how to run Daily Scrums quickly and effectively. Once they have learned to limit the Daily Scrum to 15 minutes, you can combine the teams again.

Page: 1 / 3
Total 22 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 16 Oct 2025