A Scrum Master is an important Scrum role who acts as the “servant leader” of the Scrum Team. Which of the following is a key responsibility of the Scrum Master?
The Product Owner on a project to manufacture components for engines used in submarines received feedback from the customer after the first release that there were some defects in the product, but that the product could be released despite the defects. However, if there is an increase in the number of defects, the deliverables would be rejected. This is an example of:
Mark is a member of a Scrum Team responsible for testing the code in an ongoing Sprint. Andy, the Product Owner, reassigns him to another project that needs a tester. What should Mark do in a scenario like this?
Following are some examples of risks and issues that might be encountered during the course of a Scrum project. Identify which of the following are risks, not issues.
I. After extensive training, marketing representatives might still not be ready to take orders after the project is launched.
II. The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.
III. Funding was not approved.
IV. Requirements, as currently defined, are unclear.
Which of the following statements are NOT true about a Scrumboard?
I. A Scrumboard can be maintained manually on paper or a whiteboard.
II. A Scrumboard is used by the stakeholders to plan and track progress during each Sprint.
III. A Scrumboard can contain three or four columns to indicate the progress of estimated tasks for the Sprint.
IV. A Scrumboard is created during the Create Deliverables process.
When a Scrum Team completes developing the functionalities or features they had committed to for the current Sprint, what would be the next step?
I. The Scrum Team would demonstrate the developed functionality to the end-user.
II. The Scrum Master would deliver the developed functionality to the production environment.
III. The Scrum Team would evaluate the functionality against the Acceptance Criteria.
IV. The Scrum Master might reject the developed functionality based on feedback from the stakeholders.
As defined in the SBOK Guide, which of the following is NOT a Scrum principle?
You are the Scrum Master for a power generation project. While a Sprint is in progress, the Scrum Team convinces you that the scope of the Sprint has to be changed. You plan to ask the Product Owner to allow additional User Stories to be included in the current Sprint. You remember that “a Sprint cannot be changed once the Sprint begins,” so when can the team's request be considered as an exception?
As a Scrum Master, Mike's responsibility is to facilitate Daily Standups, in which Scrum Team members assemble to discuss what they achieved yesterday, what they plan to accomplish today, and whether anything is stopping them from doing their work. The information thus collected is used for all of the following purposes EXCEPT:
Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?