Halloween Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: discbf75DC

Page: 1 / 3
Total 30 questions
Exam Code: SMC                Update: Oct 17, 2026
Exam Name: Scrum Master Certified (SMC)

Scrum Scrum Master Certified (SMC) SMC Exam Dumps: Updated Questions & Answers (October 2026)

Question # 1

A Scrum Master is an important Scrum role who acts as the “servant leader” of the Scrum Team. Which of the following is a key responsibility of the Scrum Master?

A.

Help create Project Vision Statement

B.

Identify key stakeholders of the project

C.

Ensure back-up resources are available

D.

Define Acceptance Criteria for User Stories

Question # 2

The Product Owner on a project to manufacture components for engines used in submarines received feedback from the customer after the first release that there were some defects in the product, but that the product could be released despite the defects. However, if there is an increase in the number of defects, the deliverables would be rejected. This is an example of:

A.

Risk Tolerance

B.

Risk Seeking

C.

Risk Appetite

D.

Risk Threshold

Question # 3

Mark is a member of a Scrum Team responsible for testing the code in an ongoing Sprint. Andy, the Product Owner, reassigns him to another project that needs a tester. What should Mark do in a scenario like this?

A.

Inform the Product Owner of the situation, who may extend the deadline for the current Sprint.

B.

Inform the Scrum Master of the situation, who should assign Mark's current task to someone else in the team.

C.

Inform the Scrum Master of the situation, who may discuss the situation with Andy.

D.

Inform the Product Owner of the situation, so that Mark's incomplete task is moved to the next Sprint.

Question # 4

Following are some examples of risks and issues that might be encountered during the course of a Scrum project. Identify which of the following are risks, not issues.

I. After extensive training, marketing representatives might still not be ready to take orders after the project is launched.

II. The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

III. Funding was not approved.

IV. Requirements, as currently defined, are unclear.

A.

II only

B.

I and III

C.

II and IV

D.

I and II

Question # 5

Which of the following statements are NOT true about a Scrumboard?

I. A Scrumboard can be maintained manually on paper or a whiteboard.

II. A Scrumboard is used by the stakeholders to plan and track progress during each Sprint.

III. A Scrumboard can contain three or four columns to indicate the progress of estimated tasks for the Sprint.

IV. A Scrumboard is created during the Create Deliverables process.

A.

I and II

B.

II

C.

III and IV

D.

II and III

Question # 6

When a Scrum Team completes developing the functionalities or features they had committed to for the current Sprint, what would be the next step?

I. The Scrum Team would demonstrate the developed functionality to the end-user.

II. The Scrum Master would deliver the developed functionality to the production environment.

III. The Scrum Team would evaluate the functionality against the Acceptance Criteria.

IV. The Scrum Master might reject the developed functionality based on feedback from the stakeholders.

A.

I and III

B.

II and IV

C.

All of the above

D.

None of the above

Question # 7

As defined in the SBOK Guide, which of the following is NOT a Scrum principle?

A.

Collaboration

B.

Iterative Development

C.

Manage by Stages

D.

Value-based Prioritization

Question # 8

You are the Scrum Master for a power generation project. While a Sprint is in progress, the Scrum Team convinces you that the scope of the Sprint has to be changed. You plan to ask the Product Owner to allow additional User Stories to be included in the current Sprint. You remember that “a Sprint cannot be changed once the Sprint begins,” so when can the team's request be considered as an exception?

A.

When the team has exceptionally skilled members who can multitask and help increase the value delivery of the project.

B.

When the team and Scrum Master observe that one member of the team is sitting idle.

C.

When there is a possibility of many Change Requests arising during the next Sprint.

D.

When there is an overestimation of effort during the Sprint, identified by the team and visible in the Sprint Backlog and Sprint Burndown Chart.

Question # 9

As a Scrum Master, Mike's responsibility is to facilitate Daily Standups, in which Scrum Team members assemble to discuss what they achieved yesterday, what they plan to accomplish today, and whether anything is stopping them from doing their work. The information thus collected is used for all of the following purposes EXCEPT:

A.

To identify, discuss, and resolve problems and impediments faced by Team members after the Daily Standup.

B.

To track individual Team members' performances.

C.

To track and evaluate the team's progress on the project.

D.

To identify opportunities for improvement in future Sprints.

Question # 10

Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?

A.

You should direct the Scrum Team to stop working on the current Sprint Backlog and start working on the latest business requirements.

B.

The Product Owner should add this requirement to the overall Prioritized Product Backlog, and the team would work on it in a future Sprint.

C.

You should tell the Product Owner to inform the stakeholders that this business requirement cannot be worked on because the Scrum Team has no bandwidth in the current Sprint.

D.

The Product Owner should cancel the current Sprint and start planning a new Sprint for the team to develop the deliverable according to the latest business requirement.

Page: 1 / 3
Total 30 questions

Most Popular Certification Exams

Payment

       

Contact us

Site Secure

mcafee secure

TESTED 17 Oct 2026