Question # 1

Currently, your Scrum Teams are organized to address a single functional (component) area of

the product. What should be considered when deciding to move away from such component

teams toward feature teams?

(choose the best three answers)

A.

Feature teams have less communication overhead.

B.

With feature teams, it is easier to calculate the productivity per team.

C.

You cannot do Scrum without feature teams.

D.

When making this change, it helps to have support from the organization.

E.

Productivity may decrease when making this kind of change.

Question # 2

True or False: Scrum Teams must report back to the Nexus Integration Team right after their individual Daily Scrums.

A.

True

B.

False

Question # 3

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What should the Scrum Teams do to effectively deal with their dependencies?

(choose the best answer)

A.

Increase the frequency of Cross-Team Refinement to reduce dependencies.

B.

Merge the two Scrum Teams together that have the most dependencies with each

other.

C.

Institute quarterly meetings for planning out all dependencies between teams.

D.

All of the above.

Question # 4

Which statements best describe a Nexus Sprint Review?

(choose the best two answers)

A.

It provides feedback on the Integrated Increment.

B.

It replaces individual Scrum Team Sprint Reviews.

C.

It is a container for each individual Scrum Team's Sprint Review.

D.

It is when individual Scrum Teams demo their work.

Question # 5

Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams

report that it takes many hours or days to integrate their work, which delays the Sprint's end. To

address this issue, which of the following would help?

(choose the best answer)

A.

Integrating more frequently.

B.

Doing more acceptance testing.

C.

Doing more exploratory testing.

D.

Using Behavior-Driven Development.

E.

Investing in more Requirements Traceability.

F.

All of the above.

Question # 6

You have been assigned as the Scrum Master of six new Scrum Teams that will build one

product. What conditions should you strive for in this scenario?

(choose the best two answers)

A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, one of whom is chief Product Owner.

C.

The product has one Product Backlog.

D.

There should be only one Product Owner who is accountable for the success of

the product.

E.

Each Scrum Team should have a separate Product Backlog.

Question # 7

True or False: Many Scrum Teams working on the same product create coordination

challenges that can be fully addressed by creating a communication plan.

A.

True

B.

False

Question # 8

How should Product Backlog items be chosen when multiple Scrum Teams work from the same

Product Backlog?

(choose the best answer)

A.

The Scrum Teams choose the Weighted Shortest Job First.

B.

The Developers pull work in agreement with the Product Owner.

C.

Each Scrum Team takes an equal number of items.

D.

The Scrum Team with the highest velocity pulls Product Backlog items first.

E.

The Product Owner should provide each team with its own Product Backlog.

Question # 9

The purpose of Nexus Sprint Planning is to:

(choose the best two answers)

A.

Coordinate the activities of all the Scrum Teams in a Nexus.

B.

Discover all the dependencies between Product Backlog items.

C.

Ensure all teams are committing to the right work.

D.

Create a plan for the Sprint.

Question # 10

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What techniques could help this Nexus manage their dependencies effectively?

(choose the best two answers)

A.

The Nexus Integration Team should complete the dependent work ahead of the

Sprint for the teams.

B.

Reorganize team members between the teams to eliminate cross-team

dependencies.

C.

Extend the Sprint so that the teams can have more time to complete the

dependent work.

D.

Reorder Product Backlog items to better accommodate dependencies.