Currently, your Scrum Teams are organized to address a single functional (component) area of
the product. What should be considered when deciding to move away from such component
teams toward feature teams?
(choose the best three answers)
True or False: Scrum Teams must report back to the Nexus Integration Team right after their individual Daily Scrums.
Scenario C: Dependencies and Product Backlog items
During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams
identify many dependencies. This makes it hard for them to choose the work they could pull
into their individual teams for the next Sprint. No matter how they reorganize the Product
Backlog items, they continually find more or new dependencies.
What should the Scrum Teams do to effectively deal with their dependencies?
(choose the best answer)
Which statements best describe a Nexus Sprint Review?
(choose the best two answers)
Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams
report that it takes many hours or days to integrate their work, which delays the Sprint's end. To
address this issue, which of the following would help?
(choose the best answer)
You have been assigned as the Scrum Master of six new Scrum Teams that will build one
product. What conditions should you strive for in this scenario?
(choose the best two answers)
True or False: Many Scrum Teams working on the same product create coordination
challenges that can be fully addressed by creating a communication plan.
How should Product Backlog items be chosen when multiple Scrum Teams work from the same
Product Backlog?
(choose the best answer)
The purpose of Nexus Sprint Planning is to:
(choose the best two answers)
Scenario C: Dependencies and Product Backlog items
During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams
identify many dependencies. This makes it hard for them to choose the work they could pull
into their individual teams for the next Sprint. No matter how they reorganize the Product
Backlog items, they continually find more or new dependencies.
What techniques could help this Nexus manage their dependencies effectively?
(choose the best two answers)