Question # 1

A tenant is soliciting proposals for a Commissioning (Cx) agent for Energy and Atmosphere Credit, Enhanced Commissioning. Which qualification must the agent meet?

A.

Subcontractor of construction manager

B.

Not an employee of the project design firm

C.

Member of the Building Cx Association

D.

Commissioning Authority (CxA) with experience in at least one prior project

Question # 2

For a bicycle network to demonstrate compliance with Location and Transportation Credit, BicycleFacilities, the bicycle network must connect to

A.

five bicycle trails

B.

at least eight diverse uses

C.

a restaurant, a grocery shop, a church and two bus lines

D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary

Question # 3

Which systems must be commissioned to earn Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification?

A.

Fire suppression

B.

Irrigation controls

C.

Building Envelope

D.

Daylighting controls

Question # 4

A project team is implementing a strategy that controls the admission of natural light into the office space being developed. To which credit can this contribute?

A.

Indoor Environmental Quality Credit, Interior Lighting

B.

Indoor Environmental Quality Credit, Thermal Comfort

C.

Energy and Atmosphere Credit, Advanced Energy Metering

D.

Energy and Atmosphere Credit, Optimize Energy Performance

Question # 5

Occupancy numbers must be reported consistently across multiple LEED credits. Which of the following prerequisites/credits require using the Occupancy numbers?

A.

Location and Transportation Credit, Bicycle Facilities;

Water Efficiency Credit, Indoor Water Use Reduction;

Indoor Environmental Quality Prerequisite Minimum Indoor Environmental Quality Performance

B.

Location and Transportation Credit, Access to Quality Transit;

Water Efficiency Credit, Indoor Water Use Reduction;

Indoor Environmental Quality Credit, Quality Views

C.

Location and Transportation Credit, Bicycle Facilities;

Indoor Environmental Quality Prerequisite Minimum Indoor Environmental Quality Performance;

Indoor Environmental Quality Credit, Quality Views

D.

Location and Transportation Credit, Access to Quality Transit;

Water Efficiency Credit, Indoor Water Use Reduction;

Indoor Environmental Quality Credit, Interior Lighting

Question # 6

In the pre-design phase, a plumbing engineer identified that the low-flow fixtures which met the Owner's requirements could achieve total reductions in indoor water usage of 39%. Which strategies should be assessed to meet the Owner's Project Requirements goals of 45% reduction?

A.

Switching from municipally supplied potable water to potable well water on-site

B.

Reducing irrigation needs by planting native species and drought-tolerant species

C.

Reducing potable water supply by limiting occupant access to drinking fountains and public restrooms

D.

Reducing process water demand by assessing kitchen and laundry equipment selection and operational. schedules

Question # 7

Drywall is purchased from a local manufacturer for a total materials cost of $10,000 USD. The specification of the drywall is:

· 5% of the product is comprised of post-consumer recycled paper sourced from a pulp mill 25 mi. (40 km) away;

· 50% of the product is post-consumer recycled gypsum attained from a facility 30 mi. (48 km) away;

· new gypsum is extracted from a mine 175 mi. (282 km) away.

What is the contributing value of the drywall to Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

A.

$5,500 USD

B.

$9,750 USD

C.

$11,000 USD

D.

$19,500 USD

Question # 8

To assess the feasibility of earning Location and Transportation Credit, Reduced Parking Footprint, the project team should be familiar with what local government regulation?

A.

Minimum number of parking spaces required by the local zoning code

B.

Maximum dimensions for on-street parking spaces allowed by the local zoning code

C.

Minimum number of electric vehicle charging spaces required by the local zoning code

D.

Maximum number of levels in structured parking garages allowed by the local zoning code

Question # 9

Which of the following would contribute to the Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 2. Diverse Uses?

A.

An existing bus stop located 1/4 mi. (0.40 km) away from the LEED project's main entrance

B.

An existing restaurant that is 3/4 mi. (1.20 km) away from the LEED project's main entrance

C.

An existing fast-food restaurant with no drive-in service located 1/8 mi. (0.20 km) away from the LEED project's main entrance

D.

A planned school that will be occupied within 18 months of the date of the LEED project's initial certificate of occupancy and is located 1/4 mi. (0.40 km) away from the LEED project's main entrance

Question # 10

What percentage of occupants require individual control of thermal systems under Indoor Environmental Quality, Thermal Comfort?

A.

25%

B.

50%

C.

75%

D.

90%