The TMMi process area Test Monitoring and Control has a number of specific goals. Which of the following is a specific goal of the Test Monitoring and Control process area?
Which of the following statements is TRUE regarding test process improvement in an Agile context?
Study the following description:
“Testing is multi-levelled: there are component, integration, system and acceptance test levels. For each identified test level there are specific testing objectives defined in the organization-wide or program-wide test strategy. The processes of testing and debugging are differentiated.”
To which TMMi maturity level does this description apply?
The TMMi level 2 process area Test Design and Execution has four specific goals, among others SG 2 Perform Test
Implementation and SG 3 Perform Test Execution.
Identify from the list of specific practices, a specific practice for each of the two specific goals mentioned:
I. Maintain horizontal traceabllity with requirements
II. Write test log
III. Create specific test data
IV. Track status of test incidents
During the diagnosing phase a TMMi assessment is performed to determine the current maturity status of the organization.
Which activity is performed in addition to the assessment during the diagnosing phase?
An informal TMMi assessment revealed a weakness in the area of traceability of test conditions and test cases to requirements.
Which process area are you be targeting when implementing the specific practice Maintain horizontal traceability with requirements?
A test process assessment has been performed at a small local bank. The assessment revealed that testing is performed by business analysists on an ad-hoc basis, in addition to their regular work. There are no defined test functions and testing is not considered to be a career path within the bank Which of the following process areas would need specific attention to address the above mentioned shortcoming?
Which of the following is a typical business reason for starting a test improvement program?
A test process assessment has been performed at an embedded software organization. All process areas at TMMi Levels 2 and 3 were in scope of the assessment. Many practices required by the TMMi model are already in place, but the organization is missing a master test plan spanning multiple test levels.
Which of the following process areas would most likely need specific attention to address the above-mentioned shortcoming?
Which of the following is a TMMi level 5 process area?