You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them with training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented.
Which of the following statements is true?
Where are product requirements and characteristics documented?
Giving a part of project work to a contractor is an example of:
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity.
What is the most appropriate response?
History has shown that project managers can be trained in a combination of ways.
Which method is usually preferred by most companies?
What quality control tool graphically represents how various elements of a system interrelate?
Which of the following is NOT a reason to measure variances from the baseline?
An activity-on-node (AON) network diagram shows the following activities on two critical paths; Start, D, E, J, L, End and Start, D, E, G, I, L, End. Each activity is at least three days in duration, except for activity L, which is one day in duration.
If you are directed to reduce the project by one day, which activities are MOST likely to change?
Smoothing out resource requirements from period to period is called resource _____.
As project manager, you wish to impose a standard method by which subordinates calculate project costs.
Which level of communication should be required for this effort?
If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be the cost performance index (CPI)?
Which is the total float for the activity G?
Which of the following must be taken into account for every process, even if they are not explicitly listed as inputs in the process specifications?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
An input required to develop a preliminary project scope statement is: