Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 14
Total 275 questions
Exam Code: PMI-001                Update: Oct 14, 2025
Exam Name: Project Management Professional v5

PMI Project Management Professional v5 PMI-001 Exam Dumps: Updated Questions & Answers (October 2025)

Question # 1

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Question # 2

Which is a tool used in monitoring and controlling project work?

A.

Work performance information

B.

Project management information system (PMIS)

C.

Activity duration estimates

D.

Scheduled network analysis

Question # 3

Work performance information and cost forecasts are outputs of which Project Cost Management process?

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Question # 4

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Question # 5

What is the minimum a project schedule must include?

A.

Variance analysis

B.

A planned start date and a planned finish date for each schedule activity

C.

A critical path diagram

D.

Critical chain analysis

Question # 6

What is the primary benefit of meeting quality requirements?

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

Question # 7

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.

Cost baseline

B.

Cost forecasting

C.

Cost variance

D.

Cost budgeting

Question # 8

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Question # 9

During which process does the project team receive bids and proposals?

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Question # 10

Which process occurs within the Monitoring and Controlling Process Group?

A.

Cost Control

B.

Quality Planning

C.

Quantitative Risk Analysis

D.

Cost Budgeting

Question # 11

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Question # 12

Which of the following is a tool or technique used in the Determine Budget process?

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Question # 13

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.

100

B.

120

C.

1,000

D.

1,200

Question # 14

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Question # 15

Which Control Quality tool is also known as an arrow diagram?

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

Question # 16

Administer Procurements is part of which Process Group?

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Question # 17

When does Monitor and Control Risks occur?

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Question # 18

Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?

A.

Estimate Activity Durations

B.

ControlSchedule

C.

Sequence Activities

D.

Develop Schedule

Question # 19

Which standard examines an enterprise’s project management process capabilities?

A.

PMBOK Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model “OPMJ

D.

The Standard for Portfolio Management

Question # 20

Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

A.

Risk response planning

B.

Risk monitoring and control

C.

Performance reporting

D.

Manage stakeholders

Page: 1 / 14
Total 275 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 15 Oct 2025