Question # 1

You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?

A.

Fast tracking only works if activities can be overlapped to shorten duration.

B.

Fast tracking only works if the activities are effort-driven.

C.

Fast tracking only works if the activities are resource-driven.

D.

Fast tracking only works if activities can have start-to-start relationships.

Question # 2

Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

A.

Reports

B.

Meetings

C.

Diaries

D.

Future planning

Question # 3

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?

A.

Power/interest grid

B.

Salience model

C.

Power/influence grid

D.

Communications matrix

Question # 4

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

A.

It is derived from the constraints of the project.

B.

It is assigned to the project by management.

C.

It is created by the stakeholders.

D.

It is developed from the schedule network analysis.

Question # 5

You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

A.

Stakeholder classification

B.

Project management team's classification

C.

Assessment information

D.

Identification information

Question # 6

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

A.

$227,140

B.

0.75

C.

0.95

D.

-$56,789

Question # 7

You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?

A.

$566,305

B.

$1,258,456

C.

-$54,044

D.

$503, 382

Question # 8

In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?

A.

Majority

B.

Unanimity

C.

Dictatorship

D.

Plurality

Question # 9

You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?

A.

Work performance information

B.

Project schedule

C.

Project management plan

D.

Work performance measurements

Question # 10

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?

A.

1.23

B.

100 percent because the vendor caused her lateness

C.

.80

D.

$524,000