Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dcdisc65

Page: 1 / 9
Total 84 questions
Exam Code: Prince2-Practitioner                Update: Oct 16, 2025
Exam Name: PRINCE2 Practitioner Exam

PRINCE2 PRINCE2 Practitioner Exam Prince2-Practitioner Exam Dumps: Updated Questions & Answers (October 2025)

Question # 1

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Product Summary and Product Breakdown Structure provided as additional Information for this question In the Scenario Booklet, answer the following question.

Column 1 is a list of some of the entries in the product breakdown structure. Determine whether each entry in Column 1 has been correctly shown in the product breakdown structure. Select from Column 2 the appropriate statement that correctly describes that entry. Each selection from Column 2 can be used once, more than once or not at all.

Question # 2

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Monitoring and control section?

A.

Delete entry 11 because this relates to the monitoring and controlling of the Project Plan, not the Stage Plan.

B.

No change to entry 12 because this describes how the Project Board will control the stage.

C.

Move entry 12 because the Highlight Reports are deliverables of this stage and should be shown under Product descriptions.

D.

Delete entry 13 because this is part of the Controlling a Stage process.

E.

Delete entry 14 because the Product Status Account is NOT an ad-hoc report. It is produced at the end of each stage to identify any variations between planned status, reported status and actual status of the stage's products.

Question # 3

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Plan prerequisites section?

A.

Delete entry 2 because these are project benefits not prerequisites of the stage.

B.

Delete entry 3 because the production cost forecast is a deliverable of stage 2, not a prerequisite for stage 3.

C.

Delete entry 4 because the customer list is a deliverable of stage 2, not a prerequisite for stage 3.

D.

Add 'Engineering team must be made available for photos'.

E.

Add 'Compliance with the Data Protection Act'.

Question # 4

Which of the following is not part of the composition of a Plan?

A.

Pre-requites

B.

Assumptions

C.

Quality responsibilities

D.

Product descriptions

Question # 5

Who sets the tolerances for a work package?

A.

The project board

B.

The project manager

C.

The team manager

D.

Corporate or programme management

Question # 6

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Budgets section?

A.

Amend entry 15 because it should also include the cost of management activities.

B.

Delete entry 16 because timescales should NOT be shown under the heading of budgets.

C.

Delete entry 17 because the risk budget should be shown in the Risk Management Strategy.

D.

Add 'Change budget - £500'.

E.

Add 'Cost tolerance - +£6k 1-£6k

Question # 7

Who is responsible for committing user resources to the project?

A.

Senior User

B.

Senior Supplier

C.

Executive

D.

Project Board

Question # 8

During the 'starting up a project' process, the project manager discusses the standard model for course development with the executive. The project manager then assesses how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage.

Is this an appropriate way to carry out the ‘plan the initiation stage' activity, and why?

A.

Yes, because the work of the initiation stage needs to be planned and approved, in the same way as other project work.

B.

Yes, because the management controls for the initiation stage need to be defined and approved by the project board.

C.

No, because subsequent stages are planned in the initiation stage as part of creating the project plan.

D.

No, because the senior supplier is responsible for assessing the viability of the project approach.

Question # 9

The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case.

Why is the executive's decision to deliver the benefits early appropriate for managing the business case?

A.

Because organizations with mature project management often include the early justification for the project in the business case.

B.

Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.

C.

Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.

D.

Because the business case should be updated after every increment of the 'e-learning course'.

Question # 10

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost £900. The stage 2 cost tolerance of +£1,000 has not been used. The change budget of £500 has not been used.

Which option describes how this change should be funded?

A.

£400 of the stage 2 cost tolerance and the £500 change budget should be used.

B.

£900 needed for the change should be taken from the stage 2 cost tolerance.

C.

£900 of additional funding will need to be requested to pay for the change.

D.

£400 will need to be requested in addition to the £500 change budget.

Page: 1 / 9
Total 84 questions

Most Popular Certification Exams

Payment

       

Contact us

dumpscollection live chat

Site Secure

mcafee secure

TESTED 16 Oct 2025